Line 32: Line 32:
 
# Magnet Status
 
# Magnet Status
 
# Trigger and DAQ needs during installation and commissioning.
 
# Trigger and DAQ needs during installation and commissioning.
#*  [[Private: Trigger Types]]
+
#*  [[Trigger Types]]
 
# Installation Updates (<b>Not a construction report</b>)
 
# Installation Updates (<b>Not a construction report</b>)
 
## Trigger and DAQ Installation
 
## Trigger and DAQ Installation

Revision as of 13:20, 2 August 2013

Meeting Time and Place

Friday, August 2, 2013 at 1:30 PM At Jefferson Lab, the meeting will be held in F326

Connections

To connect from the outside, please use ESNET

  1. ) ESNET: 8542553
  2. )To connect by telephone (supported on request only) dial:
  • You can look up toll-free number at http://www.readytalk.com/intl
  • US and Canada: (866)740-1260 (toll free)
  • International: (303)248-0285 (toll call)
  • enter access code followed by the # sign: 3421244#

Desktop Sharing

You can view the computer desktop in the meeting room at JLab via the web.

  1. Go to http://esnet.readytalk.com
  2. In the "join a meeting" box enter the Hall D code: 3421244
  3. Fill in the participant registration form.

Up to GlueX/Hall-D Installation Meetings

Action Items From Last Meeting

Agenda

  1. Announcements
  2. Updates to the Mechanical Installation Schedule ( Latest Rendition of Install Schedule) (Tim)
  3. Electronics Installation Schedule (Fernando) [| Schedule]
  4. Summer manpower
  5. Magnet Status
  6. Trigger and DAQ needs during installation and commissioning.
  7. Installation Updates (Not a construction report)
    1. Trigger and DAQ Installation
    2. Slow Control Installation
    3. Tagger Magnet Installation
    4. BCAL Installation
    5. FCAL Installation
    6. FDC Installation
    7. CDC Installation
    8. TOF Installation
    9. Start Counter Installation
    10. Microscope Installation
    11. Tagger Array Installation
    12. Pair Spectrometer Installation
  8. A.O.B.

Minutes