# BCAL Progress | # BCAL Progress | ||
− | ## Module 43 build will finish tomorrow; Module 44 build will finish on Friday; on schedule to complete | + | ## Module 43 build will finish tomorrow; Module 44 build will finish on Friday; on schedule to complete 45 and 46 by August 31. |
## Machining of Modules 37-40 is done. Inspection will take place tomorrow (Aug. 3) and pickup for the shipment is on August 5 with arrival at JLab on August 8. | ## Machining of Modules 37-40 is done. Inspection will take place tomorrow (Aug. 3) and pickup for the shipment is on August 5 with arrival at JLab on August 8. | ||
## Fibre QA of shipment 46: nominal atten len, Npe=7.45 +/- 0.48. | ## Fibre QA of shipment 46: nominal atten len, Npe=7.45 +/- 0.48. | ||
## Fibre Shipment 27 arrived on July 29; crate was damaged, fibres boxes inside were ok. | ## Fibre Shipment 27 arrived on July 29; crate was damaged, fibres boxes inside were ok. |
Revision as of 09:59, 2 August 2011
Teleconference Time: 11:00 a.m. EST'
- ESNET (Number is 8542553) and EVO session (GlueX Calorimetry meeting room)
- JLab Phone: in CC F326 is 757-269-6337; JLab Phone in CC L207 is 757-269-7084
- Athens Phone: in Christina's office is 011-30-210-727-6947
- Regina Phone: in LB228 is 306-585-4204
- Phone connection only upon request.
- +1-866-740-1260 : US+Canada
- +1-303-248-0285 : International
- then enter participant code: 3421244# (remember the "#").
- or www.readytalk.com (and code without the #)
Items for followup from previous meeting(s)
- Monitoring
- Zisis will remind George to send Christina some pricing information for testing of monitoring boards.
Tentative Agenda
- Announcements
- Review of Action Items
- Monitoring
- FCAL (notes from Matt)
- Construction Status: mechanical, bases
- BCAL
- Construction Status: builds, fibre QA
- Simulations
- Beam tests in Hall B (fall 2011)? (Kei)
- Any other business
Minutes
Attending:
- BCAL Progress
- Module 43 build will finish tomorrow; Module 44 build will finish on Friday; on schedule to complete 45 and 46 by August 31.
- Machining of Modules 37-40 is done. Inspection will take place tomorrow (Aug. 3) and pickup for the shipment is on August 5 with arrival at JLab on August 8.
- Fibre QA of shipment 46: nominal atten len, Npe=7.45 +/- 0.48.
- Fibre Shipment 27 arrived on July 29; crate was damaged, fibres boxes inside were ok.