Line 17: Line 17:
 
** Cabling
 
** Cabling
 
** Microscope
 
** Microscope
** Hodoscope [[image:hodo_paddle.png|thumb]]
+
** Hodoscope - plate #7 installed - 5-6mm high [[image:hodo7.png|thumb]]
 
** Target - fiducialization [[image:Target1.jpg|thumb]]
 
** Target - fiducialization [[image:Target1.jpg|thumb]]
 
** Vacuum
 
** Vacuum
Line 24: Line 24:
 
** need many cables - should limit X motion
 
** need many cables - should limit X motion
 
** Air cooled
 
** Air cooled
** supported on TAC base plate
+
** supported on TAC base plate [[Media:CPP_TAC.pdf]]
* OSP
+
* Adjustable Lead - what is the plan for usage? [[image:Adj_Lead.png|thumb]]
* Helium Bag inside CDC [[Media:CPP_TAC.pdf]]
+
* Helium Bag inside CDC [[Media:Hebag.jpg]]
 +
 
 +
== Minutes ==
 +
* Decided an OSP is needed since this is not baseline equipment. Still keep in ESAD - Elton
 +
* Rory requested practice for moving adjustable lead absorber -
 +
** Tim to write procedure
 +
** Should only need to move early in calibration mode
 +
** Tim will talk to Dave Hamlette about being able to adjust the lead without Radcon present
 +
* Six signal cables are in house and being tested
 +
* Target and helium bag
 +
** Simon and Beni would like the geometry of the target/thin windows and helium bag layout
 +
** OK to proceed with helium bag design with PVC plastic tube at upstream end

Latest revision as of 13:34, 21 April 2022

Meeting Time and Place

Thursday April 07, 2022, 3:00pm

Zoom Meeting

https://jlab-org.zoomgov.com/j/1602846419?pwd=YTNEeXI3aHBKSERjMGpsTVJZd25sQT09&from=addon

Meeting ID: 160 284 6419
  Passcode: 459361
  • Invited - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I, Anthony, Alex S., Eugene

Agenda

Minutes

  • Decided an OSP is needed since this is not baseline equipment. Still keep in ESAD - Elton
  • Rory requested practice for moving adjustable lead absorber -
    • Tim to write procedure
    • Should only need to move early in calibration mode
    • Tim will talk to Dave Hamlette about being able to adjust the lead without Radcon present
  • Six signal cables are in house and being tested
  • Target and helium bag
    • Simon and Beni would like the geometry of the target/thin windows and helium bag layout
    • OK to proceed with helium bag design with PVC plastic tube at upstream end