Hi folks:
this is a reminder for our teleconference regarding the BCAL beam tests at Hall-B on Tuesday August 29 at 12:30 EDT.
Connection
Call (306) 781-5999
Participants' code 2857251#
Agenda
- Business Arising
- Action Items (see updated list below)
- Hall-B
- Status Quo and Progress (see Beam_Test_Hardware)
- images(currently) at Installation of Module
- Electronics, Cabling see Beam_Test_Hardware and Beam Test Cabling)
- Trigger (see Beam_Test_Trigger_and_electronics)
- DAQ/Online
- Status Quo and Progress (see Beam_Test_Hardware)
- Run Plan (see Beam_Test_Run_Plan)
- Monte Carlo (see Beam_Test_Software)
- Any other business
- Software E-Log and hardbook log.
- Offline inspection (offsite?)
Action Items
- BPM, Veto: Slow control cables and stand construction pending.
- Light Leak: Module has been painted and is covered with Tedlar. Light leak test pending in alcove.
- Tagger, Trigger, Cables: The fast core cable is pending. All other cabling is nearly complete.
- Data storage/Silo Request: David and Zisis will deal with this offline.
- Online Macros/MC Data steam/MC Validation & Binning: David and Zisis will work on these offline. Zisis will provide requirements for ROOT trees.
- Safety, COOP: TOSP and ESAD are nearing completion. COOP needs to be done ~2 weeks before the run.
- Run Plan: Decide on position/angle configurations and priorities.