JEF meeting, December 6, 2024

From GlueXWiki
Jump to: navigation, search

Connection

Meeting time and location:



Agenda

Preparation of parts for ECAL -- Sasha

-Four boxes for HV distribution boards have arrived to the lab. PCBs with HV connectors were installed on 2 distribution boards [1][2]
-Updated design of the LMS light source with 25 LEDS. PCB layout under preparation, expect to order the new PCB during next week.
-Four temperature sensors (RTD) arrived to the lab. They will be installed in the ECAL divider region during next week.
-Two additional fans for cooling the ECAL dividers arrived. Will be installed today.

-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Implementing ECAL into the GlueX DAQ [3]
- rocecal3 crate was fixed [4] (initial DAQ implementation [5])
- implementing flash ADC scalers [6][7]
- translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- implementing and verifying ECAL LMS trigger [9]
- implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- New version of DAQ, VTP included as a DAQ component [11]
Meeting with Tim, additional fans will be installed
  • Repairing a few ECAL LMS optical fibers [28][29]
  • Preparing for the installation of the insulation on the detector face
- Removing Tedlar from the face of the detector [30]
- ECAL flash ADC scalers before removing detector face cover [31]
  • Preparing for the run -- Sasha
Page for shift Takers
ECAL in the Experimental Safety Assessment Document (ESAD)
EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
- Installing additional fans (will be installed today)
- Installing insulation on the detector's face (done)

Restoring PS test setup [32]

ECAL commissioning -- Sasha, All

Laveen update[[33]]

Calibrations

-First look on cosmic data -- Zhikun
-Adjusting HVs

Analysis/Simulation

Minutes

Attendees: Xiaolin, Sasha, Vlad, Zhikun, Bill, Igal, Axel, Olga, Jane, S.T.

  • 4 HV distribution boards finally arrived
    • 2 installed in hall on south side, now being cabled up
    • Installed 399 cables -> dividers, 2nd distribution box not connected yet
      • Ran scalers to check signals, found 5 swapped ables and a few other problem channels, all fixed --> scalers look ok
  • Chris S. finalizing design for LMS light source, now with 25 LEDs, will order week of Dec 9.
  • 4 temperature sensors arrived to be mounted on ECAL dividers
  • 2 fans arrived, techs will install
  • Used cosmic data to find peak positions and adjust HV (Zhikun)
    • Set amplitude goal to 9 ADC counts above base line
    • Plan to use LMS to do voltage scan, verify amplitude-hv relationship
    • May need to lower voltage to have high energy photons be in fADC range
  • Trigger development: waiting for firmware update