Run Coordinator report: spring 2019 w5
From GlueXWiki
Revision as of 17:02, 19 March 2019 by Sdobbs (Talk | contribs) (Created page with " ===RC summary, Feb. 21st -Feb. 27th 2019=== This period was mostly devoted to the start of the Primex program, with time devoted to several dedicated studies. At the start...")
RC summary, Feb. 21st -Feb. 27th 2019
This period was mostly devoted to the start of the Primex program, with time devoted to several dedicated studies. At the start of my tenure as Run Coordinator, we dedicated two shifts to some dedicated tests for the CPP experiment, in which movable lead shielding was installed in front of the TOF. These tests were completed successfully, and the setup was reconfigured the next morning from the Primex experiment.