Thursday, Nov 15 at 08:45
- Last 24h:
- Standard production running
- Issues
- CBrem gui not fitting and the coherent edge has been drifting. Decided (6am) to stop run on diamond, do Harp scan and continue with amorphous run, then TAC until the problem is fixed.
- Convergence optimization failed because optics has drifted compared to yesterday, the basis for how to carry the optimization. Rates after optimization did not show improvement.
- Beam current has been unusually unstable yesterday [Some fluctuations of current correlates with beam position drift https://logbooks.jlab.org/entry/3626367]
- Reports
- [ Monitoring] (Thomas)
- Plans
- TAC run this morning/afternoon. With V-wire
- Production running
- Discussion ComCal commissioning
- Notes