- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcement
- Optical box status
- Fabrication status update (Ernie and Jason)
- Box production at Lesker
- Mirror strong back delivery and assembly
- Mirror cutting
- Window procurement
- Assembly sequence and testing plans at Bates
- Dark box enclosure development: air flow calculations
- DIRC BBox Split Flange Seal (Jim/Tim)
- Fabrication status update (Ernie and Jason)
- Installation schedule discussion:
- Current "optimistic" schedule: optical box delivery July 14
- Contingency: Latest possible installation schedule: optical box delivery October 10
- Requirements for mechanical install of optical box: Aug 10 installation scheduledelivery required by August 10
- Mirror box laser alignment
- Update on geometry and laser projections (Bill)
- Optical Box Alignment strawman (Tim)
- Laser Alignment fixture (Tim)
- AOB