Nov. 24th 2015 meeting
- Report relevant updates from 7:50 and 8:00 daily MCC meetings:
- Accelerator has steered beam through Arc 2 by end of owl shift last night. 1090MeV per linac (=2.2GeV)
- Some accelerator tests over Thanksgiving, but tuning to 4R will not resume before Friday (i.e. accelerator is on schedule so no tuning work needed over holiday)
- Beam to Hall D is planned for Dec. 4th. It will start with beam in the tagger only for fast feedback commissioning.
- Accelerator RF trip study complete
- Link to accelerator short term schedule
- Accelerator schedule through June 2017.
- Hot Check OUT Status 27.5% ready ; 3.3% checked ; 69.2% not ready
- Report on Work in the Hall:
- If you have work to do in the Hall, please notify Tom (Hall work coordinator) and if necessary, document it in the electronic logbook.
- OSL need to be worn everywhere in Hall D.
- Fall 2015 Commissioning Plan