Trigger Commissioning
From GlueXWiki
Revision as of 17:33, 14 September 2014 by Somov (Talk | contribs) (→Phase 2: Photon Beam in the Hall)
Trigger Commissioning Plan
Phase 1: Photon-beam Commissioning
- PS stand alone trigger (2 - 3 days)
- - trigger with PSC
- - read out PS and PSC
- - trigger distribution through GTP. Use PCS self trigger if problems with GTP
Phase 2: Photon Beam in the Hall
- Tune FCAL trigger (2 - 3 days)
- - trigger using global energy
- - read out FCAL only. Raw mode for fadc250
- - adjust trigger parameters, tune timing
- - study rates for various trigger thresholds
- Add CDC, FDC, BCAL, ST, TOF (TAGM/TAGH) (4 - 5 days)
- - tune timing, adjust trigger prescalings
- Take some data for detector calibration
- - production runs during nights if the system is robust
- - run with high-energy thresholds
- - low-energy thresholds for CDC/FDC calibration