Trigger Commissioning

From GlueXWiki
Revision as of 17:25, 14 September 2014 by Somov (Talk | contribs)

Jump to: navigation, search

Trigger Commissioning Plan

Phase 1: Photon-beam Commissioning

  • PS stand alone trigger (2 - 3 days)
- trigger with PSC
- read out PS and PSC
- trigger distribution through GTP. Use PCS self trigger if problems with GTP

Phase 2: Photon Beam in the Hall

  • Tune FCAL trigger (2 - 3 days)
- trigger using global energy
- read out FCAL only. Raw mode for fadc250
- adjust trigger parameters, tune timing
- study rates for various trigger thresholds
  • Add CDC, FDC, BCAL, ST, TOF (TAGM/TAGH ?) (2 - 3 days)