Controls Meeting 15-May-2014
From GlueXWiki
Agenda
- Announcements
- Minutes from previous meeting Controls Meeting 1-May-2014
- Gas system control in PLC Media:FDC_Gas.pptx (Dave)
- EPICS GUIs for the gas system CDC/FDC_Gas_System_GUI(Mike)
- Status of TOF and tagger hodoscope voltage controls (Nerses, Vanik)
- Any other business
Minutes
Present: Dave, Mike, Nerses, Vanik, Orlando, Beni, Elton
Gas System
- Dave showed details of the gas system controls for CDC and FDC.
- Mike presented his EPICS GUIs for gas system control.
TOF voltages
- Vanik and Nerses are working on TOF voltage controls.
- Vanik showed preliminary control screens for TOF voltages.
Action items
- Dave needs to implement alarms on the supply pressure
- Mike will implement some parameters that Dave can use to adjust the cycling of the pressure measurements
- Mike will find a way to turn the gas off without changing the set-point
- Dave will check if Brooks controllers allow the valve to be shut off
- Beni wants to have a bottle at the T to run gas into CDC, Dave will set it up.
- Nerses and Vanik will finish the TOF voltages and start tagger hodoscope voltage controls