BLTWG Meeting 12/6/2007
- Time: 10:00 EST
- Place: VRVS and ESNET
- Present: Aschenauer, Jones, Klein, Whitlatch, Yang
The agenda for this meeting was to review the status of all of the major systems under the oversight of the GlueX Tagger/Beamline working group, with the purpose of setting short-term goals and target dates for accomplishing things that must be completed in preparation for the 2008 Lehmann Review.
Contents
Tagger Design
The tagger specification and Statement of Work documents for the 100% tagger engineering design bid package have been completed and sent on to purchasing for review. The 12GeV Program Office has already approved the procurement. Elke will post the final revisions of the Tagger Specification and Statement of Work documents at the usual place on the wiki. The first major milestone in the monitoring process set up for this project is in the March-April 2008 time frame. This will be finalized during negotiations with the firm who wins the contract.