Solenoid Meeting 2014-01-28
From GlueXWiki
Revision as of 11:57, 3 February 2014 by Yqiang (Talk | contribs) (Created page with "== Attendees == # George B. # David B. # Scot S. # Yi Q. == Announcement == * Spreadsheet of tasks: M:/Halld_Engineer/Solenoid/Improvements * Future Plan ** start N2 flow in Ma...")
Attendees
- George B.
- David B.
- Scot S.
- Yi Q.
Announcement
- Spreadsheet of tasks:
M:/Halld_Engineer/Solenoid/Improvements
- Future Plan
- start N2 flow in May, cryo starts in June
Minutes
Review task list
47. PXI grounding: 90% done
52. Hall-prove location - between 3 and 4, permanent, as close to center as possible. Discussion between Mark, Tom, Scot and Yi
3. LHe level probe, wiring issue - Scot
49. Coordinating system time - send PXI time to PLC - Yi
7. Sequence of Events (SOE) system done
8. More signals to SOE - refrigerator fault - firmware update - test/tweak code/ - David - in a week 85%
9. Ramp rate, front panel card fixed and installed, will test the power supply after installing the jumpers
10. Dump sequence - Giles talking to Dynfesik
11. Ground fault signal to PXI - Scot and Yi
51. Method to access old archive