Action Items from previous meetings
- Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando)
- Make a metal die to punch holes in cooling mat to ease assembly. (Nick and Jim)
- Give Jim a U-board with defective SiPM for devising extraction tool (Nick and Yi)
Tentative Agenda
- Announcements
- Action Items
- Schedule for production and testing (all)
- Schedule for production (Fernando and Jim)
- Schedule for SiPM assignment and jumper sheets
- mini-Bcal (Elton)
- SiPM production testing (Yi)
- Mechanical assembly (Jim)
- Temperature compensation (Jack)
- Electronic boards (Fernando and Chris)
- U-board puller?
- Light guide gluing setup (Scot)