Electronics Testing Readiness Review Checklist

From GlueXWiki
Revision as of 11:31, 14 September 2012 by Marki (Talk | contribs)

Jump to: navigation, search

The goal of the Electronics Readiness Review is to assess whether the University of Indiana is ready to begin production of the fabrication of the Hall D forward calorimeter modules. Specifically the following questions need to be examined:

  1. Environment
    1. General
      • Are the MSDS information sheets available for all products used during production?
      • What support do you get from university EH&S services?
      • Are there any materials (e.g cleaning agents/etc) that are of particular hazard during fabrication
  2. Procedures:
    1. Are all procedures for accepting fabricated parts documented?
    2. Are all procedures for assembling components documented?
  3. Training:
    1. What are the training procedures for first-time workers in each of the areas where they will work?
    2. How is this documented?
  4. Recovery Procedures
    1. What are the procedures for reporting an anomaly in measurements during the assembly?
  5. Tracking
    1. Are all travelers specified for the project?
    2. What information is recorded for each board?
  6. Schedule
    1. How is the schedule tracked?
    2. Note: Time for completion of a module should be revisited after the start of production.
  7. Reporting
    1. Is the reporting chain to the project clear?

Contract Requirements

  1. Final Construction Plan
  2. Final Quality Assurance Plan and Acceptance Test Plan.

Requirements and Quality Assurance: Section 3 and 4 of the Statement of Work

The vendor shall prepare a Quality Assurance and Acceptance Test Plan for approval by JLab at the Readiness Review. The following items must be included:

QA and Acceptance Test Plan (Section 4.2.1)

A Component Inspection Plan, comprised of

  1. Inspection of all materials received from the vendor’s suppliers and subcontractors and the recording of this information.
  2. Obtaining and recording of all material certifications and analyses.
  3. The calibration and identification of standards and instrumentation used for testing; the intervals between calibrations are also to be defined.
  4. Establishment of inspection points for the incoming components, which will measure critical parameters.
  5. The recording of all inspection data in such a manner so that the history of a component can be readily traced.
  6. The submittal to JLab of all data related to the above.

A Process Quality Plan, comprised of

  1. Step-by-step process documents, with instructions and prints pertaining to each assembly and/or manufacturing step.
  2. Safety information for the job operator, including material data safety sheets
  3. A method of reporting any mechanical defects found during assembly of components.
  4. A mechanism for recording all job operator work sessions.
  5. The submittal to JLab of all data related to the above.

Final Acceptance Test Plan, comprised of

  1. Acceptance of the PMTs based on their response to a nominal light source.
  2. Acceptance of the PMT bases using electrical tests.
  3. Acceptance of the lead glass bars based on their transparency and visual inspection for cracks, chips, or bubbles..
  4. Acceptance of the PMT-base-light guide assembly based on dimensional tests.

Tracking

The vendor must keep a record (travelers) of all raw materials and inspections that are used in the construction of each module, and document the procedures followed during fabrication.