May 10, 2011 SiPM Electrical and Cooling

From GlueXWiki
Revision as of 17:34, 26 April 2012 by Elton (Talk | contribs) (Action Items from previous meetings)

Jump to: navigation, search

Action Items from previous meetings

  1. Determine if swapped bias pins was accidental or in design (Chris)
  2. Develop front and back views of jumper sheets. Also get latest version of drawings (Jack)
  3. Check into AC units based on Peltier coolers for SiPM production tests (Fernando)
  4. Assemble the second SiPM puller to send to USM (Scot)
  5. Order and assemble a third SiPM puller as a backup for JLab (Jim and Scot)
  6. Setup clean tents in the ESB for gluing light guides. Prepare a plan for production testing. (Elton, Tom)

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM production testing (everyone)
  5. Mechanical assembly (Scot)
  6. Mechanical (Jim)
  7. Mechanical drawings (Chuck)
  8. Temperature compensation (Jack)
  9. Preamp-summing (Chris)

Minutes

Attending: