Sep 15, 2011 SiPM Electrical and Cooling

From GlueXWiki
Revision as of 06:45, 15 September 2011 by Elton (Talk | contribs) (Tentative Agenda)

Jump to: navigation, search

Action Items from previous meetings

  1. Investigate whether there is sufficient room to add an additional layer to the electronics at the inside of the Bcal (Fernando).
  2. Carl to check instability of LED (as a possible contributor to sensor output changes) (Carl)
  3. Bias/temperature compensation review: Tentatively set for Sep 29.

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM testing (everyone)
    1. Light source / optics
    2. Electronic boards
    3. Cabling
    4. Cooling plate
    5. Other?
    6. Discussion of Hamamatsu visit tomorrow
  5. Mechanical (Jim)
  6. Mechanical drawings (Chuck)
  7. Geometry (Elton)
  8. Temperature compensation (Jack)
  9. Preamp-summing (Fernando)
  10. Granularity (Elton)

Minutes

Attending: