Coil Test Weekly Meeting 2-Sep-2010
From GlueXWiki
Solenoid Coil Test Weekly Meeting=
Location and Time
- Thu 2-Sep-2010 9:30am ARC 428
Agenda
- Installation status
- DOE review late Sep
- two weeks notice to Errol?
- Test plan - Josh
- tags, HMI, etc.
- Conduct of Operations
- Magnet power supply and interlock commissioning - Cody
- can we turn it on yet?
- do we have strainers yet?
- Controls racks - Scot
- Strain gauge interlock
- anything else?
- PLC programming/testing status - Mark W
- backup PLC programmer - who?
- tutorial?
- UPS status - Mark W, Elliott
- relay card in interlock system
- connection to PLC
- EPICS <--> PLC communications - Wesley
- connection to guard shack
- HMI and EWEB programming - Yi, Elliott, Hovanes
- status
- tutorial?
- Coil repair status - George
- OSP documents and review - Elliott, George