Coil Test Weekly Meeting 17-Jun-2010

From GlueXWiki
Revision as of 16:07, 16 June 2010 by Wolin (Talk | contribs)

Jump to: navigation, search

Solenoid Coil Test Weekly Meeting

Note: short meeting due to Solenoid meeting at 11am


Location and Time

  • Thu 17-Jun-2010 9:30am ARC 428


Agenda

  • F117 status - Elliott
    • when to move PLC to F117 for testing?
    • hole in the wall?
  • B field - George, Floyd
  • B Field at power supply - Floyd, George
    • where to place racks?
  • Safety review - Elliott
    • 2-Jul meeting date
    • 23-Jun deadline submit writing assignments to me
    • 25-Jun submit documents to committee
    • writing assignments (SME):
      • George - pressure (Steve L), large mechanical structures (John K and/or Suresh), B field (Jennifer W)
      • Josh - ODH (Mat), cryo supply (Mat), cryo devices (Mat)
      • Cody - magnet power (Bill Merz)
      • Elliott - controls (Steve L)
    • list of previous reviews
  • Coil test plan - Josh
  • Magnet power supply commissioning - Cody
    • status
    • dump resistor
    • magnetic field
  • EPICS <--> PLC communications - Wesley
  • Relay cards (for open collector outputs) - Cody
  • Controls racks - Mark W, Scot
    • wiring diagram update
  • PLC programming status - Mark W
  • HMI and EWEB programming - Yi, Elliott
  • Printer, laptop - Elliott
  • Installation status - George
  • Coil repair status - George
  • DOE mandated coil replacement plan status - George, Elliott