Coil Test Weekly Meeting 11-Mar-2010

From GlueXWiki
Revision as of 10:43, 9 March 2010 by Wolin (Talk | contribs)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 11-Mar-2010 9:45am ARC 428


Agenda

  • Computers and accounts for coil test - Elliott
  • Safety review, ODH, etc. - Elliott, Josh
  • Final P&I diagram, machine protection, failure scenarios - Josh
  • Status of PLC programming - Mark W
  • HMI and web programming status - Yi
  • What PLC display pages do we want, and what should be archived and how often - George
    • main pages, fault pages, trends, etc.
  • Wiring progress in F117 - Scot
  • Moving into QWeak area
  • Do we want to tie into existing vent piping system - Tom
  • Status of miscellaneous parts orders - George
  • Coil 1 status - George
  • Coil 2 cost and schedule - George
  • Coil 3 statement of work, visit and IUCF contract - George, Tom
  • Coil 4 controls wiring replacement - George
  • 5 G contours - George
  • Coil Test Top To-Do items