Aug 6, 2009 Calorimetry
From GlueXWiki
Teleconference Time: 11:00 a.m. EST
- ESNET and EVO session
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 77438230# (remember the "#"). Note: code changed 7/2/09
Contents
Items for followup from previous meeting(s)
-
Procedure to avoid vaseline in Bcal fabrication needs to be approved. -
Documentation on fiber first-article - Review calibration procedures
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- FCAL Update
- BCAL Updates
- Fabrication (Zisis)
- Press Frame
- Swager/Lead
- Fibre Sorting Table
- Construction Methods
- Fibre QA (Zisis)
- Shipment03 Preliminary JPG Media:Shipment03_Preliminary.jpg
- Shipment03 Preliminary PDF Media:Shipment03_Preliminary.pdf
- Fabrication (Zisis)
- Simulations
- BCAL Readout
- Other business
Minutes
Attendees:
- Announcements
- None
- Review of Action Items
- First to items addressed. Dedicated calibration and monitoring meeting will be scheduled.
- FCAL Update
- CAN-ethernet bridge is working well. Test for use with slow controls by Claire was successful. Will be documented
- Contract
- PR for production of Fcal modules has been submitted and signed.
- Detailed cost response needs to be prepared. (Elton to send Regina docs to Matt for reference).
- FEU-84-3 pmt specs
- Matt will meet with Sergey Denisov next week. Needs to get the following information to enable the procurement to go forward:
- contact info (person as well as e-mail/address/etc)
- estimated cost
- updates to specs as suggested by Sergey. Add "not-used" to specification.
- Matt will meet with Sergey Denisov next week. Needs to get the following information to enable the procurement to go forward:
- Cosmic-ray test setup -constant progress. Hope to have something to show at collaboration meeting
- Radiation damage tests (Ryan)
- Irradiated glass blocks at cyclotron.
- Brad (student) measuring transmission of irradiated glass
- Transmission vs wavelength for various doses has been completed.
- Still need to understand how to convert of registered dose to units such as Gray.
- Magnetic shields (Tim)
- 14 mil shield has been modified to fit inside shield -> send back to Amuneal to anneal shield and ship back
- Expect receipt of annealed shield in two weeks to verify final configuration.
- How much (if any testing) can be done before shipping pmts? Should one plan to purchase more than needed and make a selection here? What fraction of rejects are expected?
- BCAL Updates
- Fabrication (Zisis)
- Press Frame
- Swager/Lead
- Fibre Sorting Table
- Construction Methods
- Fibre QA (Zisis)
- Shipment03 Preliminary JPG Media:Shipment03_Preliminary.jpg
- Shipment03 Preliminary PDF Media:Shipment03_Preliminary.pdf
- Fabrication (Zisis)
- Simulations
- BCAL Readout
- Other business