JEF meeting, April 11, 2025
From GlueXWiki
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- ECAL maintenance and performance during the run
- Issue with the FCAL HV module [1]
- Flash ADC scalers during first beam [2]
- Two modules fixed during the accelerator maintenance day [3]
- ECAL scalers after maintenance day (production at 100 nA on 4.5x10^-4 Al radiator) [4]
- Commissioning of the ECAL trigger [5] [6]
- Issues with the readout crate during two first two production nights [7]
- Calibrations
- Monitoring
- Restoring PS test setup [11]
- Assembling PS prototype [12]
Minutes
Attendees: Liping, Bill, Sasha, Jane, Drew, Axel, S.T.
- Working on setting optimum energy scaling w.r.t. the FADC range for the ECAL
- Need to set FADC channel for 9 GeV crystal energy so as to not go out of range due to energy fluctuations
- Have new guesses for ECAL HV settings based on Compton analysis; these have not been set yet.
- Use to set global scale
- Maybe ramp up HV a little?
- Had failure of one of HV modules for ECAL
- 5x5 PWO + 5x5 lead glass prototype assembled in COMCAL box, ready for installation in hall
- Using PMT dividers from Hall A for lead glass modules, need adapter for HV connector or replacement