JEF meeting, January 10, 2025
From GlueXWiki
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- -New PCB and parts for the LMS light source arrived to the lab. The LMS board will be assembled and tested during next week.
- -Consider to install two more temperature sensors (will try to fix the old ones first), a few sensors have been ordered
-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Implementing ECAL into the GlueX DAQ [1]
- - Initial version of the VTP firmware ready. Started testing using a setup with one VTP during the holiday break (some progress has been made)
- - VTPs installed on all ECAL VXS crates [2]
- - Use new version of DAQ, VTP included as a DAQ component. Will be updated on the entire detector after the ECAL commissioning
- ECAL HV interlock check [3]
- -Replace one HV module (problems with the interlock) [9]
- Update signal translation table [10]
- Update mapping of the ECAL high voltages and spare HV cables [11]
- Implement ECAL HV interlock based on the newly installed temperature sensors in the divider region [12]
- Toook cosmic data with the whole detector powered [13]
- Meeting with Tim, additional fans will be installed
- Repairing a few ECAL LMS optical fibers [18][19]
- Preparing for the installation of the insulation on the detector face
- Preparing for the run -- Sasha
- Page for shift Takers
- ECAL in the Experimental Safety Assessment Document (ESAD)
- EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
- FCAL2 Engineering Meetings
- Remaining installation tasks
- - Installing additional fans (will be installed today)
- - Installing insulation on the detector's face (done)
Restoring PS test setup [22]
ECAL commissioning -- Sasha, All
Calibrations
- Gain calibration
- Low-level timing
- Timing with respect to other detectors
Analysis/Simulation