JEF meeting, November 1, 2024
From GlueXWiki
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- - Connectors and cables were installed on the PCBs of 2 HV distribution boards. Sammy and Chris are working on the third board, it will likely be ready during next week (Sammy also works on GEM/TRD)
- - Boxes for HV boards have been just been ordered. Expected delivery date 11/15/2024.
- - Vince P. has machined parts for two temporary distribution boards. Two temporary HV distribution boards were assembled. The holes for connectors were too narrow, the tech group fixed it.
- - Have received all parts for the new version of the LMS light source
Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Installation of the light distribution board of the ECAL LMS [3]
- - Vlad P. has slightly modified the design of the LMS light source in order to increase the amount of light. Chris S. is working on a new board with 9 LEDs.
- Implementing ECAL into the GlueX DAQ [4]
- - rocecal3 crate was fixed [5] (initial DAQ implementation [6])
- - implementing flash ADC scalers [7][8]
- - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [9]
- - implementing and verifying ECAL LMS trigger [10]
- - implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [11]
- - Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- - The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- Installation of scintillating paddles for cosmic tests [12] [13][14]
- ECAL HV interlock check [15]
- Cable map of the ECAL LG modules after installing ECAL [16]
- Reinstalling cables on the ECAL LV distribution board [17]
- Safety briefings - Vlad, Sasha
- Detector installation page
- Installation of temporary HV distribution boards and testing flash ADC scalers [18][19][20]
- FCAL2 Engineering Meetings
- Remaining installation tasks
- - Connecting cooling pipes to the ECAL fan (done by tech group)
- - Installing dark room ceiling and insulation inside the room, required for cooling test (almost complete)
- - Test cooling system (in progress, almost complete)
- - Installing HV distribution boards, start switching the detector ON (waiting for HV boxes)
Restoring PS test setup [21]
ECAL commissioning -- Sasha, All
Calibrations
Analysis/Simulation
- Update from Zhikun [22]
Presentation at IEEE [23]
- Conference trip was not supported by Hall D
Minutes
Attendees: Sasha, Liping, Igal, Xiaolin, Laveen, Olga, Vlad, Phil, Axel, Jane, Zhikun, S.T.
- No news on HV boxes, still expect November 18 delivery
- Using 2 temporary boxes allowing checking 1/2 ECAL
- Read out flash-ADC scalers using LED light source at 500 Hz
- Found several holes due to slightly disconnected dividers, now fixed
- Some problems appear to be due to jostling of chains (maybe need more than velcro to tie together? Metal rods?)
- Found swapped cables
- Found bad connector on PCB
- One problem with LV distribution: baseline shift
- Read out flash-ADC scalers using LED light source at 500 Hz
- Checking other 1/2 will have to wait for real HV box/board solution
- Using 2 temporary boxes allowing checking 1/2 ECAL
- Using 2 chillers keeping temperature at 19 C to avoid condensation
- Need to check temperature stability
- Blow air on ECAL dividers
- Will install dehumidier(s)
- LMS: working on increasing light output -- would like to increase 10x
- Considering whether or not we need integrating sphere
- Inject light directly? Working on alternate solution with small aperture LEDs
- Work to begin on infrastructure for reference PMT + radioactive source
- DAQ: next step is to start reading out waveforms
- Zhikun showed hit occupancy plot for FCAL-2 using simulated muon events
- Discussed plans for beam tests using PS
- 5x5 array lead glass + 5x5 array lead tungstate (have spares, can reuse ComCal box
- Measure position resolution with 5x5 lead tungstate array?
- Hakob willing to come in January to help maintain detector, maybe work on veto prototype?