February 08, 2023 Tech group meeting
From GlueXWiki
Revision as of 17:59, 7 February 2023 by Whitey (Talk | contribs) (Created page with "= Meeting Time and Place == Wednesday February 08, 2022 10am TED 2561 and Teams == Agenda == * Safety - SLAC incident * Emails older than 7 years will be deleted - can arch...")
Meeting Time and Place =
Wednesday February 08, 2022 10am TED 2561 and Teams
Agenda
- Safety - SLAC incident
- Emails older than 7 years will be deleted - can archive up to 15 years - memo come out soon
- Inclusion survey - 72% staff participation
- Raises and Promotions - TRC complete - will set by March
- EIC CD-3A review - to start spending money
- Deputy WC interviews complete - request to hire submitted to HR
- 2023 wellness program to offset insurance cost
- Worker safety committee needs volunteers
- All 16 gauge extension chords to be taken out of service - only by 12 gauge from now on
- FCAL2 current Tasks
- Schedule updated
- FCAL2 Design tidbits
- Monitoring panel discussion - waiting on Sasha
- Cabling/patch panels - Waiting on Sasha
- need cooling pipe to chiller assy
- need dark room mod for electronic patch panels, need to complete 0200 final assy dwg
- Rack platform
- need installation drawing
- outer plexiglass
- Tungsten - waiting on monitoring decision
- Insulation
- Man lifts - Scot renting one
- Liftable frame mods
- Cable trays
- drip pan
- FCAL2 Assembly
- Assemble FCAL2 step plates/cooling blocks - completed - will go with what we have and address during assy
- Epoxy fittings to Cooling Manifold
- Bend/solder copper tubes - complete
- JBweld conductive epoxy tubes to blocks
- HDList updates - weekly!
- Shims needed for assy
- KLONG dwgs
- On Call -