Run Planning Meeting Notes, Novemver 17 - Novemver 23, 2022
From GlueXWiki
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Contents
Sunday, November 20
Past 24 hours
- XB collected (111505-present)
Shift Summary
- [0400-1000 20/11]
- [2200-0400 19-20/11]
- [1600-2200 19/11]
- 1000-1600 19/11
- 0400-1000 19/11
Issues/Reports
- 10B collected since the start of this Full target cycle (111456-present)
Plan
- Take Full target data until Monday morning
- Acc. White Board, no maintenance scheduled for next week
- Priority to Hall C until 24/11
- Priority to Hall A 25/11 to ??/??
Saturday, November 19
Past 24 hours
- 3.3B collected (111492-present)
Shift Summary
Issues/Reports
- FCAL bases lockup (5 cases in 24hrs), Malte noted that the lockup frequency is higher when the target is filled compared to empty target periods.
- Goniometer was in BLANK position instead of RETRACTED
- 10B collected since the start of this Full target cycle (111456-present)
Plan
- Take Full target data until 13B triggers reached
- Acc. White Board, no maintenance scheduled for next week
- Priority to Hall C until 24/11
- Priority to Hall A 25/11 to ??/??
Friday, November 18
Past 24 hours
- 2.7B collected (111480-present)
- 2hrs lost due to RF
Shift Summary
Issues/Reports
- FCAL base lockup
- Beam current slightly higher than 200nA (Alexandre D.)
- 6.7B collected since the start of this Full target cycle (111456-present)
Plan
- Take Full target data until 13B triggers reached
- Acc. White Board, no maintenance scheduled for next week
- Priority to Hall C until 24/11
- Priority to Hall A 25/11 to ??/??
Thursday, November 17
Past 24 hours
- 2.8B collected (111460-present)
- 2hrs lost because of DAQ issue
Shift Summary
Issues/Reports
- Non regular beam energy (Keigo/Victor)
- FCAL base lock
- CDC IA was not turned on after the target was filled (Ellie/Thomas)
- DAQ issue (Sergey/Ellie/Thomas)
- 3.83B collected since the start of this Full target cycle (111456-present)
Plan
- Take Full target data until 12B triggers reached(?)
- Expect downtimes and unstable beam due to Hall A spin dance & 70uA beam
- Acc. White Board, no maintenance scheduled for next week
- Priority to Hall C until 24/11
- Priority to Hall A 25/11 to ??/??