CPP Run Coverage Summer 2022
From GlueXWiki
Revision as of 08:23, 11 May 2022 by Elton (Talk | contribs) (Created page with " {| class="wikitable" style="text-align: center;" |+ Time estimates for Run Plan |- ! Activity !! Duration (PAC Days) !! Duration (hours) !! Current !! Target !! Collimator...")
Activity | Duration (PAC Days) | Duration (hours) | Current | Target | Collimator | Radiator | Comment |
---|---|---|---|---|---|---|---|
Full target (Production) | 20 | 960 | 27 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | Alternate 0/90 deg diamond configuration |
TOF, CDC HV Scans | 0.2 | 10 | 27 nA | - | 3.4 mm | AMO (1x10-4) | Need time to assess data before updating settings. FCAL/BCAL trigger |
Empty Target | 1.5? | 72 | 27 nA | - | 3.4 mm | JD70-103 or JD70-107 | Run at higher current? |
Diamond Alignment | 0.5? | 24 | 20 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 and JD70-107 | |
Trigger Commissioning | 1? | 48 | 100 nA? | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | |
Lead Shield Alignment | 0.2 | 10 | 30-100 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | |
Beam Energy Calibration | 0.1? | 5 | 100 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | Collimator Blocking for 5 min, periodically |
Straight Track (Solenoid off) | 0.5? | 24 | 100 nA? | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | Ramping magnet takes about a shift. |
PS magnet at GlueX nominal current | 0.1? | 5 | 27 nA? | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | |
TAC Runs | 1.5? | 72 | <2 nA | - | 3.4 mm | AMO (2x10-5) | |
All Non-production total | 5.6 | 269 | - | - | - | - | - |