Run Planning Meeting Notes, Jan 16-Jan 22, 2020
From GlueXWiki
Thursday, January 16 at 08:45
- Last 24 hours
- Trippy beam yesterday and overnight. Issues in two cryomodules.
- Some production data was collected.
- L1 triggers studies have been postponed to today.
- Issues
- Major bleed through, presumably from Hall A 1-pass beam 3764868
- Tasks for today
- After spin dance (11 am -3 pm in accelerator plan): L1 triggers studies (Sasha, Beni, Justin)
- Followed by cDAQ test (Sergey)
- Production data otherwise
- Plan for later
- Tagger accidental study (Richard). Tomorrow early a.m.? Will contact RadCon for final ok. Richard's proposal
- Empty target run (target will already be emptied for accidental study).
- Discussion of 24 GeV physics came up, physics ideas are welcome.
Friday, January 17 at 08:45
- Last 24 hours
- High rate scan [1]
- cDAQ
- TOF scan
- DIRC
- Issues
- Tasks for today
- Production data taking
- RF recovery starting at 9 am
- Accidental study (Richard), 1 pm. 2100 nA beam, most HVs will be turned off, empty target. RadCon will monitor. Richard's proposal
- Empty target run (2 hr)
- Plan for later
- Happy three day weekend! 🙂 Production data. No studies or downtime planned until Tuesday.
- Next meeting: Tuesday