Fall 2019 TRD/GEM Commissioning
From GlueXWiki
Revision as of 15:53, 14 December 2019 by Jrsteven (Talk | contribs) (Created page with " ==== Straight-track data ==== * For alignment of the GEM/TRD we need to acquire production samples with the magnetic field off * Straight-track sample at each of the 3 TRD p...")
Straight-track data
- For alignment of the GEM/TRD we need to acquire production samples with the magnetic field off
- Straight-track sample at each of the 3 TRD positions with the full GEM readout for tracking and alignment studies
- Beam LEFT: Runs 70703-70721 taken with FCAL_TRACK_LEFT configuration
- Beam RIGHT: Runs 70728-70751 taken with FCAL_TRACK_RIGHT configuration
- Beam CENTER: Runs 70757-70786 taken with FCAL_TRACK_CENT configuration
Full GEM readout: tracking mode
- The electronics for three of the GEM packages are readout limited to ~3kHz
- At least one large dataset at each of the 3 TRD positions will be required with the full readout for tracking and alignment studies with the full solenoid field
- Beam CENTER: Runs 70868-70992 taken with FCAL_TRACK_CENTER configuration
- Beam LEFT: Runs 71013-????? taken with FCAL_TRACK_LEFT configuration