Run Planning Meeting Notes, Oct 11-Oct 17, 2018
From GlueXWiki
Thursday, Oct 11 at 08:45
- Notes from the past 24 hours:
- Beam issues most of swing (7hrs to do amorphous run) and owl shift.
- CEBAF
- 5th pass separator failed during swing shift and into the beginning of owl. Beam back at 3:20am.
- PSS drop in the machine at 3:30 am. No beam until 6am.
- Action Items
- Issues
- Need to schedule a TAC run
- Can we do this opportunistically?
- Use bleedthrough current?
- Hall C plans to switch experiments on approximately the 22nd. This is around the time of accelerator maintenance, so they may plan to switch experiments then.
- MyaViewer missing events
- Need to schedule a TAC run
- Reports
- [ Monitoring Report]
- Plot Browser
- Rate and Energy Monitoring
- Run Plan
- AOB