September 8, 2011 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • Status
    • Additional testing procedures
    • First package tests (Lubomir)
  2. Engineering update (Bill)
  3. Electronics update (Chris)
    • New testing card for the cathodes
  4. Chamber testing at EEL126 (cell#2) (Beni)
  5. Other

Minutes

Participants: Bill, Dave, Simon, Beni, Elton, Mark, and Lubomir.

Production

- Dave: The capacitors were changed on all wire frames needed for the first production package. Wires frame #6 was populated, wires deadened and will be put in package today or tomorrow. Wire frame #7 is out of the stringing table and Chris will put the elements on it tomorrow. The last two cathodes for the first package: started putting the rigid-flexes on type-1; on type-2 the frame was glued and on Monday the Mylar foil will be glued.

- After testing the first cell of the production package we found the following problems:

  • One wire was broken between the pad and the epoxy