Jan 24, 2011 Calibration/Monitoring
From GlueXWiki
Teleconference Time: 09:00 CST (Regina) / 10:00 EST / 17:00 GMT+2 (Athens)
- ESNET preferred, EVO as a backup
Background information
- Monitoring R&D issues for the relative gain calibration and monitoring system for the calorimeters and possibly other detector systems.
- Calibration Specifications Table for BCAL, FCAL, TOF and START
- Oct 26, 2010 Calibration/Monitoring minutes
- Nov 23, 2010 Calibration/Monitoring minutes
- Nov 30, 2010 Calibration/Monitoring minutes
- Dec 06, 2010 Calibration/Monitoring minutes
Tentative Agenda
- Review goals/objectives of Monitoring system and past discussions.
- George Voulgaris' slides: Media:AnswersaboutLED.pdf
- Discuss Matt's suggestion: groove in light guides, radial fibres. (sent as email)
- Summarize info, prepare recommendations and discuss it in Working Group to reach conclusion and proceed with Athens Construction MOU (decision by May 2011).
Minutes
Attendees: Christina (Athens), Elton (JLab), Zisis (Regina)
- Review goals/objectives and background information:
- Revised ETC request timetable for the BCAL/FCAL Monitoring Project will indicate May 2011 - April 2012. There is a reasonably firm plan for the FCAL and the same needs to be achieved for the BCAL by May or sooner.
- Dynamic range of SiPMs is planned to be 400. Andrei's plots show at least 200, so there is some safety margin built in.
- George Voulgaris' slides:
- Discuss Matt's idea:
- Summarize info: