JEF meeting, February 7, 2025

From GlueXWiki
Revision as of 10:24, 7 February 2025 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

Connection

Meeting time and location:

Agenda

Preparation of parts for ECAL -- Sasha

-New LMS light source is ready [1]. Will be installed and checked during next week. Parts for holding reference PMTs are ready.

-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Implementing ECAL into the GlueX DAQ [2]
- Six VTPs have been installed, firmware loaded
- Testing GTP trigger using individual ECAL VXS crates [3]
  • Commissioning the entire detector using the LMS (signal waveforms)
- Signal waveforms after resolving issues with the ECAL modules [4]
- Long-term stability check [5]
List of cosmic runs
  • ECAL HV interlock check [6]
  • HV module failed during cosmic run [7]
  • Tuning HV settings [8]
  • Material in front of the ECAL, TOF absorber [9][10]
  • Temperature scan in the ECAL divider region [11][12][13]
Fans replaced in the central region [14]
Lower detector high voltages [15]
Temperature of the NPS detector[16]
2 temperature sensors in the divider region connected, fan included into the detector interlock [17] -- Josh, Bobby
Temporary temperature sensors installed in the ECAL region [18]
  • Preparing for the run -- Sasha
Page for shift Takers
ECAL in the Experimental Safety Assessment Document (ESAD)
EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)

Restoring PS test setup [19]

Working on the plan for testing calorimeter prototype

ECAL commissioning -- Sasha, All

Calibrations

- Update on calibration with cosmic rays [20] -- Zhikun

Abstract for the SPIE conference

Preparations for readiness review