Run Planning Meeting Notes, August 3- August 10, 2022
From GlueXWiki
Revision as of 17:14, 3 August 2022 by Deurpam (Talk | contribs) (Created page with " Back to Run Coordination Meetings:Summer2022 Meeting are via ZoomGov: [https://jlab-org.zoomgov.com/j/1601990060?pwd=TUtwTGszMFg5bjhwdC9nU0IvREUzZz09 connect] (Meeting I...")
Back to Run Coordination Meetings:Summer2022
Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Wednesday August 3
Past 24 hours
Shift Reports
- Day shift summary
- Swing shift summary
- [ Owl shift summary]
- [ Early Riser shift summary]
Reports
Issues
Plans
- Production running on empty target until Thursday
- Thursday morning, TAC run starting ~9am (7-8 hours, assuming stable beam)
- RF Recovery for 4hrs on Friday to prepare for weekend
- Monday day: 5 -> 4 pass change for Hall C