Dec 6, 2019 Engineering Group Meeting
From GlueXWiki
Meeting Time and Place
Friday Dec 6, 2019 at 2pm At Jefferson Lab, room TED 2504
Agenda
- ESH&Q minute -
- Workers Safety Committee - Keith
- New rules for working on Electrical equipment
- Checklist Required (Class and Mode)
- Log entry or HDLisT required
- Training
- Property
- General Access
- Budget - Continuing resolution 90% of last years monthly charges
- Accelerator Status - Run through Dec 19, 6am, start up Jan 10, 2020- May 2020, down until Jan 2021
- Media:Accel_schedule.pdf
- 2021 and 2022, run Jan - Sept straight
- What needs to be done in the meantime?
- Dec 9-13 Move GEM 2 more times (Solenoid at 1350A)
- Dec 10 Install BR Crystal testing station and check out PS magnet
- Dec 18 Ramp down Solenoid? and Separate FCAL platform and Install Halo Shield on TOF
- Dec 19 Remove GEM from DIRC Platform and install BL DS of PS
- Dec 20 Prepare Hall for vacation
- Jan 7-10 Couple FCAL platform and prepare Hall for beam (some subset of HCO TBD)
- Continue FCAL Insert Design (Keith H)
- Start CPP Design Media:CPP_Concept.pdf
- Hot Check Out https://accweb.acc.jlab.org/hco/checklists
- Hall D operations https://halldweb.jlab.org/hdops/wiki/index.php/Information_for_Experts
- Hall D Maintenance Log https://halldweb.jlab.org/cgi-bin/maintenance/cgi/status.pl