Coil Test Weekly Meeting 3-Jun-2010
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 3-Jun-2010 9:30am ARC 428
Agenda
- Coil test schedule - all
- Safety review update - Elliott
- 2-Jul preliminary meeting date
- 24-Jun deadline for writing assignments
- Coil test plan - George, Josh
- Update on safety interlock design - Mark S, Scot
- fast and slow dump circuits
- redundancy in power supply overcurrent interlock
- Magnet power supply commissioning - Cody
- dump resistor
- magnetic field
- upgrade to higher current
- Update on EPICS <--> PLC communications - Wesley
- Magnetic field near control racks and computers - George
- Final A-B equipment order - Elliott
- Wiring and testing controls racks - Scot
- how do we test the system in F117?
- when does the PLC need to move to F117?
- PLC programming status - Mark W
- C-glass calibrations - George
- HMI and EWEB programming - Yi, Elliott
- Installation status - George
- Coil repair status - George