JEF meeting, December 20, 2024

From GlueXWiki
Revision as of 12:46, 3 January 2025 by Somov (Talk | contribs) (Minutes)

Jump to: navigation, search
Connection =

Meeting time and location:


Agenda

Preparation of parts for ECAL -- Sasha

-Four boxes for HV distribution boards have arrived to the lab. PCBs with HV connectors were installed on 2 distribution boards [1][2]
-Updated design of the LMS light source with 25 LEDS. PCB layout under preparation, expect to order the new PCB during next week.
-Four temperature sensors (RTD) arrived to the lab. They will be installed in the ECAL divider region during next week.
-Two additional fans for cooling the ECAL dividers arrived. Will be installed today.

-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Implementing ECAL into the GlueX DAQ [3]
- rocecal3 crate was fixed [4] (initial DAQ implementation [5])
- implementing flash ADC scalers [6][7]
- translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- implementing and verifying ECAL LMS trigger [9]
- implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- New version of DAQ, VTP included as a DAQ component [11]
  • Installation of scintillating paddles for cosmic tests [12] [13][14]
  • ECAL HV interlock check [15]
  • Cable map of the ECAL LG modules after installing ECAL [16]
  • Reinstalling cables on the ECAL LV distribution board [17]
  • Safety briefings - Vlad, Sasha
  • Detector installation page
  • Commissioning north part of the ECAL (instrumented with 2 temporary HV distribution boards) [18][19][20][21][22]
  • Commissioning of the south bottom region [23]
  • Commissioning of the south top region [24]
  • Commissioning of the top north region [25]
  • Commissioning of the bottom north region [26]
  • All HV distribution boards installed, set HV on the whole detector [27]
  • Fix LV issues (north top region) [28]
  • First cosmic event in the ECAL [29]
  • Temperature scan in the ECAL divider region [30][31][32]/4321188[33]
Meeting with Tim, additional fans will be installed
  • Repairing a few ECAL LMS optical fibers [34][35]
  • Preparing for the installation of the insulation on the detector face
- Removing Tedlar from the face of the detector [36]
- ECAL flash ADC scalers before removing detector face cover [37]
  • Preparing for the run -- Sasha
Page for shift Takers
ECAL in the Experimental Safety Assessment Document (ESAD)
EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
- Installing additional fans (will be installed today)
- Installing insulation on the detector's face (done)

Restoring PS test setup [38]

ECAL commissioning -- Sasha, All

Laveen update[[39]]

Calibrations

-First look on cosmic data -- Zhikun
-Adjusting HVs

Analysis/Simulation

Minutes

Attendees: Bill, Phil, Igal, Liping, Sasha, Vlad, Zhikun, Jane, Laveen, Jane, Zisis

  • 2 HV distribution boards installed on the north side
    • Arranged and connected all cables
    • Fixed several issues on the top north
      • 2 connectors have broken lock clip, 2 connectors have small hole
      • long screws were pushing on the multi-pin connectors attached to the CAEN modules (Sammy came to the hall and resolved the problems)
    • Problem with one HV channel on the bottom north; unable to hold high voltage above 1 kV. The problem was on one of PCBs. Reconnected cable to the spare channel (too much work to uninstall the board)
    • Powered up the entire detector and checked with the LMS
      • minor issues with some modules, loose connection of the PMT socket (fixed)
      • all ECAL channels are operational
      • need to restore the HV cable mapping in the CSS after installing the final distribution boards
  • Temperature sensors arrived and have been installed


  • LV problem for North top fixed (was drawing 4 Amps)
    • Consider lower trip setting for LV?
  • 3D printing for reference PMT (for LMS) setup sarted
  • Chris S. working on final layout for LMS light source (with 25 LEDs), to order the week of 9/16/24, receive next year?
  • Temperature sensors arrived and have been installed
  • 2 new fans have been installed
    • Need to be put into interlock