Run Planning Meeting Notes, January 19 - January 25, 2023
From GlueXWiki
Thursday January 19
Past 24 hours
- Ran on empty target until 7:20am. Then, beam was taken away for beam and RF study and acceptable beam came back only Thursday at 1:10am. ABU= 4h for the day
- refilled the target around 4:15pm.
- Several accesses done during the day:
- Scott
- Sergey
- David Lawrence
- Cody
- Took amorphous data, starting around 1:10am after aborted attempt to check diamond alignment.
Shift Reports
Reports
- Harp scans (just our harp)
- Hovanes attempted to start diamond alignment between 10:50pm-1am. Not able to start due to lack of good beam.
Issues
- TOF rate issues (Beni)
- beam energy oscillation
- 30% increase in transmission compared to Summer 2020 run.
Plans
- Beam off starting around 10am for RF study, nominally until 4pm+/-4h.
- Hall in controlled access?
- Diamond alignment: Friday day ? (Hovanes unavailable today)
- Until Friday day, production on amorphous?
- Link to runplan