+ | == Friday, February 7 == | ||
+ | # Last 24 hours | ||
+ | #* Production runs @350nA until 14:00 | ||
+ | #* Hovanes worked on diamond position for JD70-105 0/90 (see reports) | ||
+ | #* Continued data taking until 18:15 | ||
+ | #* Connection issues with rocDIRC -> Bill, Sergey and network expert on call had to work until late night to fix the problem | ||
+ | #* Accelerator crew was having network issues too | ||
+ | # Issues | ||
+ | #* DIRC cart leaking (see: [https://logbooks.jlab.org/entry/3779122]) | ||
+ | #* Problems with 1L12 and 2L24 (see: [https://logbooks.jlab.org/files/2020/02/3779188/Screenshot%20from%202020-02-07%2004-06-43.png]) | ||
+ | #* Accelerator site having problems with IOCs in alarm handler (see: [https://cebaf.jlab.org/dtm/open-events?event_id=6073]) | ||
+ | # Reports | ||
+ | #* New diamond position for JD70-105 0/90 (see: [https://logbooks.jlab.org/entry/3778980],[https://logbooks.jlab.org/entry/3779032]) | ||
+ | #* Communication problems with rocDIRC (see: [https://logbooks.jlab.org/entry/3779047],[https://logbooks.jlab.org/entry/3779095],[https://logbooks.jlab.org/entry/3779158]) | ||
+ | #* Network problems on accelerator site (see: [https://logbooks.jlab.org/entry/3779159],[https://logbooks.jlab.org/entry/3779161]) | ||
+ | # Plans for today | ||
+ | #* Production runs | ||
+ | |||
== Thursday, February 6 == | == Thursday, February 6 == | ||
# Last 24 hours | # Last 24 hours |
Revision as of 08:07, 7 February 2020
Friday, February 7
- Last 24 hours
- Production runs @350nA until 14:00
- Hovanes worked on diamond position for JD70-105 0/90 (see reports)
- Continued data taking until 18:15
- Connection issues with rocDIRC -> Bill, Sergey and network expert on call had to work until late night to fix the problem
- Accelerator crew was having network issues too
- Issues
- Reports
- Plans for today
- Production runs
Thursday, February 6
- Last 24 hours
- Beam was sent to hall at 19:51
- Harp scans (see reports for details)
- Production runs @ 350nA
- Collected 1.8B events
- Issues
- DIRC temperature alarm (resolved, see: [11])
- Swing shift reported coherent peak for JD70-105 0/90 PARA to be unusually wide -> No such observations for other settings
- Reports
- Harp scan results: acc: 5C11,acc: 5C11B, Hall D: TAGH
- Test of DIRC communication algorithm (see: [12])
- Missing optical links in DIRC (see: [13])
- Plans for today
- Production runs