== Tuesday, January 25 at 08:45 == | == Tuesday, January 25 at 08:45 == | ||
# Last 24 hours | # Last 24 hours | ||
− | #* | + | #* First day of production with 350nA beam current! |
# Issues | # Issues | ||
#* TOF point disappearance after window shift [https://logbooks.jlab.org/entry/3772058], [https://logbooks.jlab.org/entry/3772122] | #* TOF point disappearance after window shift [https://logbooks.jlab.org/entry/3772058], [https://logbooks.jlab.org/entry/3772122] |
Revision as of 16:13, 27 January 2020
Contents
Tuesday, January 25 at 08:45
- Last 24 hours
- First day of production with 350nA beam current!
- Issues
- Reports
- Plans for today
- No beam study / RF recovery planned
- Diamond alignment later this week
Monday, January 24 at 08:45
- Last 72 hours
- Issues
- Reports
- Tasks for the today
- Increase beam current to 350nA
- Switch off low-energy TagH counters (new EPICS configuration file) [13]
- No beam study / RF recovery planned
- Diamond alignment later this week
- Increase beam current to 350nA
Friday, January 24 at 08:45
- Last 24 hours
- Issues
- Frozen total PS/FCal rates fixed (Hovanes)
- Goniometer image missing [16]
- Reports:
- Updated sigmas for harp fitting tool [17]
- Monitoring Plots
- HOSS Training (David)
- Tasks for the today and the weekend:
- Empty target run after the meeting if beam is taken away
- PS Timing Studies (Friday)?
- Production
- CCAL anode study (Saturday)?
- Monday:
- Increase beam current to 350nA
Thursday, January 23 at 08:45
- Last 24 hours
- Issues
- Reports:
- Transmission [33]
- Tasks for today
- Production
- DOE tour in Hall B/C (8:00 - 12:00?)
- Spin dance (12:00?)
- Plan for later
- CCAL anode study?
- Alternative diamond alignment
- ST trigger?