Difference between revisions of "Run Planning Meeting Notes, Jan 23-Jan 29, 2020"
From GlueXWiki
(→Thursday, January 23 at 08:45) |
(→Thursday, January 23 at 08:45) |
||
Line 7: | Line 7: | ||
#* Various accelerator problems: Arc PS, Injector, Cavity HV [https://logbooks.jlab.org/entry/3768576] | #* Various accelerator problems: Arc PS, Injector, Cavity HV [https://logbooks.jlab.org/entry/3768576] | ||
#* Check-out of PS, TagM, TagH, ST after timing window shift [https://logbooks.jlab.org/entry/3768077] | #* Check-out of PS, TagM, TagH, ST after timing window shift [https://logbooks.jlab.org/entry/3768077] | ||
− | #* Harp Scan | + | #* Harp Scan [https://logbooks.jlab.org/entry/3768676] |
#* Continue production with 250nA beam current | #* Continue production with 250nA beam current | ||
# Issues | # Issues |
Revision as of 22:18, 22 January 2020
Thursday, January 23 at 08:45
- Last 24 hours
- Issues
- Tasks for today
- Production
- DOE tour in Hall B/C (8:00 - 12:00?)
- Plan for later
- SC Trigger?