(Thursday, Feb. 28 at 08:45)
(Thursday, Feb. 28 at 08:45)
Line 19: Line 19:
 
# Today (Thursday):
 
# Today (Thursday):
 
#* Remove Be foil @ 8 AM, but leave cylindrical holding tube.  Lockup hall at ~1 pm
 
#* Remove Be foil @ 8 AM, but leave cylindrical holding tube.  Lockup hall at ~1 pm
#* Production running with no target until 6 am Friday morning?
+
#* Production running with no target until 6 am Friday morning
 
# Friday plan:
 
# Friday plan:
 
#* LHe target installation:  
 
#* LHe target installation:  
Line 26: Line 26:
 
# LHe target cooldown and filling schedule?
 
# LHe target cooldown and filling schedule?
 
#* Chris expects ~10-12 hours required for cooldown.  He would like to be here during the initial fill.
 
#* Chris expects ~10-12 hours required for cooldown.  He would like to be here during the initial fill.
#* Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Monday?
+
#* Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Sunday/Monday?

Revision as of 09:32, 28 February 2019



Thursday, Feb. 28 at 08:45

  1. Past 24 hours:
  2. Today (Thursday):
    • Remove Be foil @ 8 AM, but leave cylindrical holding tube. Lockup hall at ~1 pm
    • Production running with no target until 6 am Friday morning
  3. Friday plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline
      • Other work in the Hall: start counter installation, others?
  4. LHe target cooldown and filling schedule?
    • Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
    • Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Sunday/Monday?