Line 81: | Line 81: | ||
==General Information== | ==General Information== | ||
− | This document describes the run plan for the Hall D | + | This document describes the run plan for the Hall D Spring 2019 run. |
* Schedule for the run: | * Schedule for the run: | ||
# Jan. 22nd - 29th: Electron beam restoration | # Jan. 22nd - 29th: Electron beam restoration | ||
− | # Jan. 30th - Feb. 12th: 2-weeks DIRC Commissioning (Solenoid at nominal field. LH2 target) | + | # Jan. 30th - Feb. 12th: 2-weeks DIRC Commissioning <font color="blue">(Solenoid at nominal field. LH2 target)</font>) |
− | # Feb. 12th - Apr. 7th: 8.5-weeks PrimEx-eta run (Solenoid off. <font color=" | + | # Feb. 12th: <font color="red">1 day of CPP test?? (Solenoid at nominal field. LH2 target)</font>) |
+ | # Feb. 12th - Apr. 7th: 8.5-weeks PrimEx-eta run (Solenoid off. <font color="magenta">No target, then Be then <sup>4</sup>He target </font>). | ||
# Nominally, every Mondays: 12h of beam study. Every Tuesdays, if necessary: 8h of RF recovery. | # Nominally, every Mondays: 12h of beam study. Every Tuesdays, if necessary: 8h of RF recovery. | ||
Line 95: | Line 96: | ||
* [https://halldweb.jlab.org/wiki/index.php/Spring_2019_DIRC_Commissioning DIRC commissioning page] | * [https://halldweb.jlab.org/wiki/index.php/Spring_2019_DIRC_Commissioning DIRC commissioning page] | ||
* <font color="red">PrimeX run page</font> | * <font color="red">PrimeX run page</font> | ||
+ | * DAQ and Trigger high-intensity tests during DIRC commissioning. | ||
+ | * <font color="red">CPP tests drug last day of DIRC commissioning?</font> | ||
+ | * Parasitic TRD runs. | ||
* <font color="red">Test fast raster beam envelope measurement with larger x-rastering? </font> | * <font color="red">Test fast raster beam envelope measurement with larger x-rastering? </font> | ||
− | * | + | * Strait track runs not |
* Expected Staffing and responsibilities: | * Expected Staffing and responsibilities: | ||
**The Run Coordinator oversees the commissioning: | **The Run Coordinator oversees the commissioning: | ||
*** Jan. 22nd-Jan. 29th, 7 days: Alexandre Deur (accelerator restoration) | *** Jan. 22nd-Jan. 29th, 7 days: Alexandre Deur (accelerator restoration) | ||
− | *** Jan. 30th-Feb. 13th, | + | *** Jan. 30th-Feb. 13th, 14 days: Alexandre Deur |
*** Feb. 13th-Feb. 20th, 7 days: Colin Gleason | *** Feb. 13th-Feb. 20th, 7 days: Colin Gleason | ||
*** Feb. 20th-Feb. 27th, 7 days: Sean Dobbs | *** Feb. 20th-Feb. 27th, 7 days: Sean Dobbs |
Revision as of 08:02, 18 January 2019
Contents
Spring 2019 GlueX Run
Meeting General Agenda
Connect Information
To connect from the outside by phone please do the following
1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.
2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.
3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.
4.) The moderator code is 8394
Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Specific instructions for connecting from JLab's Hall D conference room:
- Turn polycon on if necessary (do it before turning the computer on)
- With the polycon, place a call at 199.48.152.152
- Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
- You may have to unmute the microphone: #*4
- Turn the computer on if needed
Beam and Hall configuration
- Beam energy expected:
- 11.630 GeV (10 MeV less than value for Fall 2016 to Fall 2018 up Nov. 15th, due to imbalanced linac setting).
- Solenoid:
- DIRC commissioning: 1350A
- PrimEx-eta run: off
- CW Beam:
- 250 MHz frequency.
- Range:
- DIRC commissioning: 50 nA-1.2 μA.
- PrimEx-eta run: 1 nA-500 nA. ??
- Chopper slit: shared with Hall C until 03/10/2019. Then alone on slit A.
- Standard current and radiators
- DIRC: Standard commissioning current: 225 nA on 1.4·10-4 R.L. radiator (JD70-104 17 μm diamond).
- DIRC: Hight intensity tests: 1.2 μA on 1.4·10-4 R.L. radiator (JD70-104 17 μm diamond) (or 0.5 μA on JD70-105, 47 μm diamond of 3.9·10-4 R.L.)
- PrimEx-eta run: Standard production on 4He: 320 nA. on 10 µm Al (11.2·10-5 R.L.)
- PrimEx-eta run: Standard production on Be: 30 nA. on 30 µm Al (33.7·10-5 R.L.)
- RSAD limit for most of the run, excluding high intensity tests: ?? nA on ??·10-4 R.L. radiator.
- Position Slow Lock on or FFB on (FFB doesn't operate below 50nA).
- Radiators:
- Goniometer radiators:
- Diamond JD70-104 (17 μm - 1.4·10-4 R.L., 7×7 mm²) - wider rocking curve - Tested in Spring 2018 and used at the beginning of Fall 2018. Probably has some radiation degradation.
- Diamond JD70-105 (47 μm - 3.9·10-4 R.L., 7×7 mm²) - Used for the second part of GlueX's Fall 2018 run. Good performance.
- 40 μm Al radiator (44.9·10-5 R.L.)
- V-wire (for TAC run).
- Amorphous
- 1.64 µm Al (1.86·10-5 R.L., see study)
- 10 µm Al (11.2·10-5 R.L.)
- 30 µm Al (33.7·10-5 R.L.)
- Goniometer radiators:
- Tagger quadrupole on (-4.2 A).
- Collimator hole: Both 5 mm diameter and 3.4 mm diameter. Default running: 5.0 mm.
- Targets:
- LH2 target: cryogenic target
- 4He target: cryogenic target
- Be target 18 mm, 5·10-4 R.L. </font>
- Miscellaneous:
- CPP (Charged pion polarizability) tests
- To be set-up and done during the last day of DIRC allocated commissioning time.
- Use LH2 target, keep solenoid on at nominal field, DIRC stays in nominal position.
- Move downstream platform downstream
- Install passive shielding in front of TOF.
- Tests (to be done at various positions of passive shielding).
- End of test: remove shielding, ramp down solenoid.
- Transition Radiation Detector in the Hall
- Parasitic
- CPP (Charged pion polarizability) tests
General Information
This document describes the run plan for the Hall D Spring 2019 run.
- Schedule for the run:
- Jan. 22nd - 29th: Electron beam restoration
- Jan. 30th - Feb. 12th: 2-weeks DIRC Commissioning (Solenoid at nominal field. LH2 target))
- Feb. 12th: 1 day of CPP test?? (Solenoid at nominal field. LH2 target))
- Feb. 12th - Apr. 7th: 8.5-weeks PrimEx-eta run (Solenoid off. No target, then Be then 4He target ).
- Nominally, every Mondays: 12h of beam study. Every Tuesdays, if necessary: 8h of RF recovery.
- Accelerator overall plan and priorities:
- Deliver physics beam to 4 halls. (Hall A stop early, on March. 10th. Halls B and or C will always be at 5th pass, so Hall D beam will always be RF-separated.)
- DIRC commissioning page
- PrimeX run page
- DAQ and Trigger high-intensity tests during DIRC commissioning.
- CPP tests drug last day of DIRC commissioning?
- Parasitic TRD runs.
- Test fast raster beam envelope measurement with larger x-rastering?
- Strait track runs not
- Expected Staffing and responsibilities:
- The Run Coordinator oversees the commissioning:
- Jan. 22nd-Jan. 29th, 7 days: Alexandre Deur (accelerator restoration)
- Jan. 30th-Feb. 13th, 14 days: Alexandre Deur
- Feb. 13th-Feb. 20th, 7 days: Colin Gleason
- Feb. 20th-Feb. 27th, 7 days: Sean Dobbs
- Feb. 27th-March 6th, 7 days: Justin Stevens
- March 6th-March 13th, 7 days: Alexander Austregesilo
- March 13th-March 20th, 7 days: TBD
- March 20th-March 27th, 7 days: Richard Jones
- March 27th-Apr. 3rd, 7 days: TBD
- Apr. 3rd-Apr. 7th, 4 days: TBD
- The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (M. Stevens) verify that the proper safety rules are followed. PDL is:
- Lubomir Penchev
- The analysis coordinator (Alexander Austregesilo) oversees the off-line diagnostic of the different systems and analysis of the data.
- Shifts: 2 persons per shift.
- The Run Coordinator oversees the commissioning:
- Coordination Activities:
- The RC will attend the MCC meetings at 7:45am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
- Daily run meetings broadcasted on Bluejeans will occur at 8:45am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.
- Useful links:
- Accelerator schedule
- Link to Richard Jones program to plot the beam profile at the collimator.
- Links to previous runplans
- Links to beam parameters/radiation level monitoring:
- Last 8-hours plots showing 1-minute, 10-minute, and hourly averages
- Same but Last 24-hours
- Same but Last 72-hours
- Week, month, and quarter (3 months) plots also exist, with similar web addresses.
- A map of the radiation monitors
Runplan
Hall D situation room (current run plan)
Hall D counting room white board
Runplan time charts
Accelerator status
Hot Checkout
- Hot Check OUT Status 0% ready ; 0% checked ; 100% not ready
Readiness for Fall 18 run
- Solenoid (Eugene/Beni)
- Surveys (Tim/Mark)
- DAQ (Sergei).
- Trigger (Alex S.)
- Beam line
- Diamond status (Tim/Hovanes).
- Discussion to install a low quality thick diamond (U.Conn. inventory) for DIRC commissioning: Schedule is too tight.
- Tagger hodoscope (A. Somov)
- Tagger microscope (Beni/Richard Jones)
- All electronic has been turned on. Richard is checking the signals.
- Goniometer (Hovanes).
- Collimator, Active collimator, profiler, luminosity monitor (Hovanes/Alexandre Deur).
- Act. Col. baselines have been zeroed mid July 2018 and checked on 08/15. To be checked before Spring 2019 run.
- luminosity monitor
- PS system (Alex Somov)
- Beam line magnets (PS magnet sweeping magnet and tagger quads).
- Polarimeter (Sebastian Cole/M. Dugger).
- LH2 Target (Tim/Alexandre D.)
- Be target
- TAC (Hovanes/Alex Somov)
- Plan to cured (oven) after the Fall 2018 run?
- During TAC runs. TAC to be inserted on beam line with 2cm offset to avoid damaged area
- Plan to cured (oven) after the Fall 2018 run?
- Slow control (Hovanes).
- RF (Elton/Beni)
- Radiation monitors (Alexandre D.)
- Halo Monitors (Hovanes)
- Diamond status (Tim/Hovanes).
- Detector systems
- ST (Mark Ito)
- FDC (Lubomir)
- CDC (Beni)
- BCal (Elton/Mark D.)
- FCal (Collin Gleason)
- ComCal (Alex Somov)
- TOF (Mark Ito/Beni/Alex. Ostrovidov)
- DIRC (J. Stevens)
- RSAD and ESAD Safety documents (Lubomir):
- Phones
- System experts need to start looking for their on-call phones
- Hall Status/safety (Mark/Tim)
- Other topics?