Difference between revisions of "December 3, 2018 DIRC"
From GlueXWiki
(Created page with "== Meeting Information == GlueX DIRC Meeting<br> Monday December 3, 2018<br> 1:00 pm, EDT<br> JLab room A110<br> == Connection Using Bluejeans == # To join via Polycom room...") |
(→Agenda) |
||
Line 20: | Line 20: | ||
# Optical box | # Optical box | ||
#* Fabrication status update (Ernie and Jason) | #* Fabrication status update (Ernie and Jason) | ||
− | #** Box window flange modification at Lesker (Ernie/Tim) | + | #** Box window flange modification at Lesker complete (Ernie/Tim) |
− | #*** Lower (beam right) box at JLab | + | #*** Lower (beam right) box at JLab |
+ | #**** Depth measurements taken this morning | ||
+ | #**** Interference between large flat mirror and window flange [https://halldweb.jlab.org/wiki/images/c/c5/IMG_20181203_100045872.jpg] [https://halldweb.jlab.org/wiki/images/4/4e/IMG_20181203_101814250.jpg] [https://halldweb.jlab.org/wiki/images/1/11/IMG_20181203_123415690.jpg] | ||
#*** Upper (beam left) box arrived at JLab on Friday. | #*** Upper (beam left) box arrived at JLab on Friday. | ||
#** LED fiber feedthroughs and diffuser | #** LED fiber feedthroughs and diffuser |
Revision as of 13:46, 3 December 2018
Meeting Information
GlueX DIRC Meeting
Monday December 3, 2018
1:00 pm, EDT
JLab room A110
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcements
- All components need to be at JLab and tested by end of December, in preparation for January install
- Optical box
- Fabrication status update (Ernie and Jason)
- Box window flange modification at Lesker complete (Ernie/Tim)
- LED fiber feedthroughs and diffuser
- ThorLab diffuser and fiber coupling tests (Bill)
- Diffuser location and projected angles (Stephanie)
- Dark box enclosure: fabrication, testing, and delivery to JLab (Jason)
- Quartz window RTV after measurement of lower box at JLab. Delivery schedule? (Ernie)
- Testing at JLab
- Laser alignment test in ESB: starts this week (Bill)
- Fabrication status update (Ernie and Jason)
- PMT fit results (Andrew)
- Software/simulations
- Addressing ERR review recommendations
- Recommendations pertaining to DIRC commissioning should be addressed before installation.
- AOB