Difference between revisions of "Run Planning Meeting Notes, Oct 25-Oct 31, 2018"
From GlueXWiki
(→Thrusday, Oct 25 at 08:45) |
(→Thursday, Oct 25 at 08:45) |
||
Line 7: | Line 7: | ||
#* Hall is in controlled access | #* Hall is in controlled access | ||
#* Accell. | #* Accell. | ||
− | #** Extended phaser studies into swing-shift | + | #** Extended phaser studies/tests into swing-shift |
#** Master Oscillator Modifications (MoMod) ~8h begin in swing-shift | #** Master Oscillator Modifications (MoMod) ~8h begin in swing-shift | ||
#* Earliest to expect beam: Around owl-shift (i.e. Friday) | #* Earliest to expect beam: Around owl-shift (i.e. Friday) | ||
Line 15: | Line 15: | ||
# Plans | # Plans | ||
#* Today | #* Today | ||
− | #** Work in hall? | + | #** Work in hall? Need to go into restricted access? |
#** Set shifts on standby until 8:00am tomorrow? | #** Set shifts on standby until 8:00am tomorrow? | ||
#* Upcoming days | #* Upcoming days |
Revision as of 08:39, 25 October 2018
Thursday, Oct 25 at 08:45
- Last 24h
- Took data with 180nA beam until 9:00am
- Emptied target, coll. to block, gon. to blank
- FCAL Base replacements
- Issues and current Status
- Hall is in controlled access
- Accell.
- Extended phaser studies/tests into swing-shift
- Master Oscillator Modifications (MoMod) ~8h begin in swing-shift
- Earliest to expect beam: Around owl-shift (i.e. Friday)
- Reports
- Plans
- Today
- Work in hall? Need to go into restricted access?
- Set shifts on standby until 8:00am tomorrow?
- Upcoming days
- Take data as soon as beam is available
- Accel. plans RF recovery for Tuesday, need to re-tune one of the cavitis
- Today
- AoB