(Created page with "___TOC___ == Original Plan == * August 22 to October 28 9.5 Weeks of Running Complete GlueX Phase I * October 29 to November 19 3 Weeks Installation of CompCal and DIRC...") |
(→Modified Plan at Collaboration Meeting) |
||
Line 5: | Line 5: | ||
* November 19 to December 19 4 Weeks CompCal and DIRC Commissioning | * November 19 to December 19 4 Weeks CompCal and DIRC Commissioning | ||
== Modified Plan at Collaboration Meeting == | == Modified Plan at Collaboration Meeting == | ||
+ | * September 28 to November 10 6 Weeks GlueX Phase I | ||
+ | * November 11 to November 25 2 Weeks CompCal Installation (DIRC Installation as possible) | ||
+ | * November 26 to December 19 3 Weeks CompCal Commissioning |
Revision as of 09:16, 9 October 2018
_ _Original Plan
- August 22 to October 28 9.5 Weeks of Running Complete GlueX Phase I
- October 29 to November 19 3 Weeks Installation of CompCal and DIRC
- November 19 to December 19 4 Weeks CompCal and DIRC Commissioning
Modified Plan at Collaboration Meeting
- September 28 to November 10 6 Weeks GlueX Phase I
- November 11 to November 25 2 Weeks CompCal Installation (DIRC Installation as possible)
- November 26 to December 19 3 Weeks CompCal Commissioning