Line 8: | Line 8: | ||
== Wednesday, Oct 3 at 08:45 == | == Wednesday, Oct 3 at 08:45 == | ||
# Notes from the previous 24 hours: | # Notes from the previous 24 hours: | ||
− | #* [https://logbooks.jlab.org/entry/3603333 | + | #* [https://logbooks.jlab.org/entry/3603333 Cryo target issue] |
#CEBAF: | #CEBAF: | ||
#Action Items: | #Action Items: |
Revision as of 16:22, 3 October 2018
<- Back to Run Coordination Meetings:Fall2018 Run
- Trigger Spreadsheet Started Filling out on 9/28/18
- Run Plan Google Calendar
- Accel. Plan Google Calendar
Wednesday, Oct 3 at 08:45
- Notes from the previous 24 hours:
- CEBAF:
- Action Items:
- Microscope occupancy is still unreliable - should be fixed when Richard has loaded new thresholds
- Definition of nominal coherent peak energy
- Issues:
- placeholder
- Reports:
- Monitoring
- Run Plan:
- Week 2 Week 3 Week 4
- TAC run prep on Thursday
- 0930 Quick access for Hovanes with ARM to install the Pb converter; also remember to call Melvin from radcon to fix the alarm (number on whiteboard & alarm)
- Hovanes will calibrate A.C. high gain setting on Thurs am.
- TAC run on Friday
- Hall C will be down from 7am for 6-8h
- MCC need ~2h to set up low current, ETA 0830-0900, setup DAQ (~1h, Sasha), take data for 4-5h. (Go to 30nA & V-wire if we run out of single-hall time).
- Acc whiteboard
- Counting house whiteboard
- AOB