Line 2: | Line 2: | ||
* [http://calendar.google.com Google Calendar] | * [http://calendar.google.com Google Calendar] | ||
+ | |||
+ | ==Friday, April 15== | ||
+ | |||
+ | # Accelerator Status | ||
+ | #* Beam went down at 8am Tuesday for beam studies. Expected back at noon. | ||
+ | #* ion chambers calibrated .... maybe | ||
+ | #* Running with 5th-pass separator | ||
+ | #* Hall-B becomes priority 15:00 Friday | ||
+ | # Hall-D/GlueX items | ||
+ | #* '''NO PARKING ON SOUTH OR NORTH SIDE OF ROAD''' | ||
+ | #* Latest scans: [https://logbooks.jlab.org/entry/3398835 5C11,5C11B] , [https://logbooks.jlab.org/entry/3398835 Hall-D] | ||
+ | #* Collimator Motor not responding | ||
+ | #* Empty run complete | ||
+ | #* TRD Run complete | ||
+ | #* Trigger Studies | ||
+ | #* Quadrupole Test complete | ||
+ | #* Tagger Microscope alignment complete | ||
+ | #* other systems? | ||
+ | # Run Plan | ||
+ | #* TRD run '''~1hr''' (Lubomir, Sergey) | ||
+ | #* Trigger Studies | ||
+ | #** Requires individual thresholds | ||
+ | #* Active Collimator Raster - Todd/Richard | ||
+ | # Offline analysis? | ||
+ | #* [https://logbooks.jlab.org/entry/3398923 Vertex Distributions] (Simon) | ||
+ | #* [https://logbooks.jlab.org/entry/3398795 Accidental \rho& rates vs. collimator size] (Justin) | ||
+ | # AOB? | ||
==Thursday, April 14== | ==Thursday, April 14== | ||
Revision as of 08:06, 15 April 2016
Contents
Friday, April 15
- Accelerator Status
- Beam went down at 8am Tuesday for beam studies. Expected back at noon.
- ion chambers calibrated .... maybe
- Running with 5th-pass separator
- Hall-B becomes priority 15:00 Friday
- Hall-D/GlueX items
- NO PARKING ON SOUTH OR NORTH SIDE OF ROAD
- Latest scans: 5C11,5C11B , Hall-D
- Collimator Motor not responding
- Empty run complete
- TRD Run complete
- Trigger Studies
- Quadrupole Test complete
- Tagger Microscope alignment complete
- other systems?
- Run Plan
- TRD run ~1hr (Lubomir, Sergey)
- Trigger Studies
- Requires individual thresholds
- Active Collimator Raster - Todd/Richard
- Offline analysis?
- Vertex Distributions (Simon)
- Accidental \rho& rates vs. collimator size (Justin)
- AOB?
Thursday, April 14
- Accelerator Status
- Beam went down at 8am Tuesday for beam studies. Expected back at noon.
- ion chambers calibrated .... maybe
- Running with 5th-pass separator
- Hall-B becomes priority 15:00 Friday
- Hall-D/GlueX items
- Latest scans: 5C11,5C11B , no Hall-D harp scan
- High Luminosity Test
- JD70-119 20um
- 200nA, 250nA, 300nA, 350nA, 400nA (runs 11359-11363)
- CDC inner ring HV current limit raised from 12uA to 16uA (restored after)
- TAC run complete
- TRD run
- Quadrupole measurement
- other systems?
- Run Plan
- Empty Target Run
- TRD run ~1hr (Lubomir, Sergey)
- Trigger Studies - NO PARKING ON SOUTH SIDE OF ROAD
- Requires individual thresholds
- Quadrupole test (partial progress1partial progress2partial progress3)
- Production running on 50um diamond
- Mode 8 run w/ Amorphous ~1hr
- Active Collimator Raster
- Offline analysis?
- AOB?
Wednesday, April 13
- Accelerator Status
- Beam went down at 7am Tuesday for SL work followed by 5th pass separator test. It was gone until~2am.
- Ion chambers not reporting since 3/27
- Hall-A getting 5-pass beam
- Beam studies starting ~8am Thursday
- Hall-B becomes priority 15:00 Friday
- Hall-D/GlueX items
- Solenoid Incident
- CDC Repairs, Area survey for magnetic materials
- Solenoid ramped to 1200A without incident
- Online Monitoring
- Occupancy Plots
- Latest scans: 5C11,5C11B , Hall-D harp scan
- Current fluctuations
- other systems?
- Solenoid Incident
- Run Plan
- TRD runs ~1hr (Lubomir, Sergey)
- TAC Run
- Trigger Studies
- Tagger alignment ~1hr (Alex B.)
- Mode 8 run w/ Amorphous ~1hr
- Halo Linearity scan (Hovanes)
- Harp scan collection
- Production running on 50um diamond
- Parasitic quadrupole test (partial progress1partial progress2)
- Parasitic DAQ livetime/RAID test
- Offline analysis?
- AOB?
https://logbooks.jlab.org/entry/3398268
Tuesday, April 12
- Accelerator Status
- Beam went down at 7am for work in SL.
- Accelerator will investigate going back to 5th pass separation. If possible, Hall-A will use 5 pass beam. If not, they will use 4 pass.
- Beam expected back late during swing shift or early owl
- Hall-D/GlueX items
- Solenoid Incident
- Initial indications
- Assessment and Repair plan
- Safety walkthrough
- Online Monitoring
- https://logbooks.jlab.org/entry/3397771 Pulser Trigger]
- Latest scans: 5C11,5C11B , Hall-D harp scan
- other systems?
- Solenoid Incident
- Run Plan
- Mode 8 run w/ Amorphous ~1hr
- TRD runs ~1hr (Lubomir, Sergey)
- Halo Linearity scan (Hovanes)
- Harp scan collection
- Production running on 50um diamond
- Parasitic quadrupole test (partial progress)
- Parasitic DAQ livetime/RAID test
- Offline analysis?
- AOB?
Monday, April 11
- Accelerator Status
- Beam went down at 7am for radcon survey of SL
- Hall-A going to 2 pass (will take a couple of hours. Estimate is to come back ~10am)
- "... blind ..."
- Hall-D/GlueX items
- Solenoid Trip
- Latest scans: 5C11,5C11B , Hall-D harp scan
- Beam current Stability
- Rates and Live times
- other systems?
- Run Plan
- Mode 8 run w/ Amorphous ~1hr
- TRD runs ~1hr (Lubomir, Sergey)
- Halo Linearity scan (Hovanes)
- Harp scan collection
- Production running
- Parasitic quadrupole test
- Parasitic DAQ livetime/RAID test
- Offline analysis?
- AOB?