Difference between revisions of "Run Planning Meeting Notes, April 11-April 18, 2016"
From GlueXWiki
Line 15: | Line 15: | ||
#* other systems? | #* other systems? | ||
# Run Plan | # Run Plan | ||
+ | #* TRD runs '''~1hr''' (Lubomir, Sergey) | ||
+ | #* TAC Run | ||
#* <font size="+4">Trigger Studies</font> | #* <font size="+4">Trigger Studies</font> | ||
+ | #* Tagger alignment '''~1hr''' (Alex B.) | ||
#* Mode 8 run w/ Amorphous '''~1hr''' | #* Mode 8 run w/ Amorphous '''~1hr''' | ||
− | |||
#* Halo Linearity scan (Hovanes) | #* Halo Linearity scan (Hovanes) | ||
#* Harp scan collection | #* Harp scan collection | ||
Line 24: | Line 26: | ||
#** Parasitic DAQ livetime/RAID test | #** Parasitic DAQ livetime/RAID test | ||
# Offline analysis? | # Offline analysis? | ||
− | |||
# AOB? | # AOB? | ||
Revision as of 23:44, 12 April 2016
Wednesday, April 13
- Accelerator Status
- Beam went down at 7am Tuesday for SL work followed by 5th pass separator test. It was gone until ...
- Hall-D/GlueX items
- Solenoid Incident
- CDC Repairs, Area survey for magnetic materials
- Solenoid ramped to 1200A without incident
- Online Monitoring
- Occupancy Plots
- Latest scans: 5C11,5C11B , Hall-D harp scan
- other systems?
- Solenoid Incident
- Run Plan
- TRD runs ~1hr (Lubomir, Sergey)
- TAC Run
- Trigger Studies
- Tagger alignment ~1hr (Alex B.)
- Mode 8 run w/ Amorphous ~1hr
- Halo Linearity scan (Hovanes)
- Harp scan collection
- Production running on 50um diamond
- Parasitic quadrupole test (partial progress)
- Parasitic DAQ livetime/RAID test
- Offline analysis?
- AOB?
https://logbooks.jlab.org/entry/3398268
Tuesday, April 12
- Accelerator Status
- Beam went down at 7am for work in SL.
- Accelerator will investigate going back to 5th pass separation. If possible, Hall-A will use 5 pass beam. If not, they will use 4 pass.
- Beam expected back late during swing shift or early owl
- Hall-D/GlueX items
- Solenoid Incident
- Initial indications
- Assessment and Repair plan
- Safety walkthrough
- Online Monitoring
- https://logbooks.jlab.org/entry/3397771 Pulser Trigger]
- Latest scans: 5C11,5C11B , Hall-D harp scan
- other systems?
- Solenoid Incident
- Run Plan
- Mode 8 run w/ Amorphous ~1hr
- TRD runs ~1hr (Lubomir, Sergey)
- Halo Linearity scan (Hovanes)
- Harp scan collection
- Production running on 50um diamond
- Parasitic quadrupole test (partial progress)
- Parasitic DAQ livetime/RAID test
- Offline analysis?
- AOB?
Monday, April 11
- Accelerator Status
- Beam went down at 7am for radcon survey of SL
- Hall-A going to 2 pass (will take a couple of hours. Estimate is to come back ~10am)
- "... blind ..."
- Hall-D/GlueX items
- Solenoid Trip
- Latest scans: 5C11,5C11B , Hall-D harp scan
- Beam current Stability
- Rates and Live times
- other systems?
- Run Plan
- Mode 8 run w/ Amorphous ~1hr
- TRD runs ~1hr (Lubomir, Sergey)
- Halo Linearity scan (Hovanes)
- Harp scan collection
- Production running
- Parasitic quadrupole test
- Parasitic DAQ livetime/RAID test
- Offline analysis?
- AOB?